Pool renovation I Leak in Can Picafort

Leak in the skimmer pipes repaired and pipe route to the plant room renewed. Comprehensive refurbishment with new waterproofing, stairs, bench and mosaic.

Where?
Can Picafort
Service
Pool renovation I Leaking

About the pool project in Can Picafort

In this project, the initial focus was on detecting leaks - the cause was in the skimmer pipes. After completely replacing the pipes and the skimmer, the pool was extensively renovated, resealed and fitted with a modern mosaic and a staircase and bench solution.

Working at the pool:

  • Pool checked for leaks, leaks detected on the skimmer lines
  • Natural stone cover removed - pipe path from the skimmer to the technical room completely opened
  • Concrete opened in the area of the skimmer (approx. 70 cm)
  • Old pipes removed and two new skimmers with new pipes installed up to the plant room
  • All old tiles removed
  • Openings made in the area of the nozzles, floor drains and light pots
  • New staircase and bench concreted and integrated
  • New nozzles, new floor drain and light pots installed and set in concrete
  • Basin ground down to the concrete
  • Glass fiber fabric applied to bridge cracks
  • Waterproofing with Mapelastic Smart in three layers
  • Tiling with new mosaic tiles, stairs and bench designed with white mosaic tiles for better visibility
  • Grouting with epoxy grouting material, polished to finish
  • New lighting installed